Installing The New Upper Driver Crush Zone Supports and Wiring In New Front Blinkers
Today, we accomplished two primary tasks: 1) began the process of updating the front blinkers 2) fabricated, installed, and painted the new upper driver crush zone supports


Fabricating The New Windshield and Attempting To Set Up The Telemetry
Today, we accomplished two primary tasks: 1) fabricated and installed the new Lexan windshield 2) installed a new wifi router and attempted to communicate with the Mate3 wirelessly


Installing Flexnet DC and Strengthening Front Support of Solar Panel Array
Today, we accomplished four primary tasks: 1) installed the Flexnet DC in the cockpit and routed the wires 2) installed the Mate3 on the dash and routed the Cat 5 cable back to the communication hub 3) installed the communication hub and neatly routed the wires into and out of it. 4) reinstalled some support bracing for the front of the solar panel array